ITAC Assessment: DS0139
ITAC logo
ITAC Assessment: DS0139
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Plastics forms
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 133,000
ft2
Annual Production 4,029,592
lb
Production Hrs. Annual 8,616
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $294,178 8,971,571
kWh
Electricity Demand $141,410 18,132
kW-mo/yr
Electricity Fees $1,475 -
Natural Gas $4,056 725
MMBtu
LPG $2,891 216
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,878 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,768

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Administrative Changes Savings
01 2.3132: Recharge batteries on during off-peak demand periods $560 $270 - $560
-
kW-mo/yr
- -
02 2.4221: Install compressor air intakes in coolest locations $882 $500 $667
20,223
kWh
$215
-
kW-mo/yr
- -
03 2.4239: Eliminate or reduce compressed air usage $1,693 $391 $1,272
38,687
kWh
$421
-
kW-mo/yr
- -
04 3.4116: Meter recycled water (to reduce sewer charges) $595 $800 - - $595
-
Tgal
-
05 4.211: Consider use / purchase of bulk materials where possible $1,515 $3,300 - - - $1,515
06 4.515: Install shelves / racks to utilize unused space $2,633 $7,000 - - - $2,633
TOTAL RECOMMENDED $7,878 $12,261 $1,939
58,910
kWh
$1,196
-
kW-mo/yr
$595
-
Tgal
$4,148
TOTAL IMPLEMENTED $5,768 $8,161 $1,939
58,910
kWh
$1,196
-
kW-mo/yr
- $2,633
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs