| Assessment Year | 2011 |
|---|---|
| Principal Product | Fabric tension structures |
| NAICS | 314910: Textile Bag and Canvas Mills |
| SIC | 2394: Canvas and Related Products |
| Sales Range | $5 M to 10M |
| # of Employees | 65 |
| Plant Area |
76,000
ft2
|
| Annual Production | 1,000
pieces
|
| Production Hrs. Annual | 2,871
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $38,908 | 587,440 |
kWh
|
$0.066 |
| Electricity Demand | $27,670 | 3,278 |
kW-mo/yr
|
$8.44 |
| Electricity Fees | $4,236 | - |
|
- |
| Natural Gas | $43,931 | 4,591 |
MMBtu
|
$9.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,080 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.512: Condense operation into one building | $17,750 | $20,000 |
$1,520
66,200
kWh
|
$8,700
-
kW-mo/yr
|
$1,660 |
$5,870
-
MMBtu
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,300 | $110 |
$740
12,000
kWh
|
$560
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,530 | $31,210 |
$6,380
91,400
kWh
|
$2,920
-
kW-mo/yr
|
- | - | $130 | $100 | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $2,470 | $20,920 |
$(-260.0)
(-3,600)
kWh
|
$(-100.0)
-
kW-mo/yr
|
- |
$2,830
-
MMBtu
|
- | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $1,030 | $90 |
$570
9,300
kWh
|
$440
-
kW-mo/yr
|
- | - | $20 | - | |
| TOTAL RECOMMENDED | $32,080 | $72,330 |
$8,950
175,300
kWh
|
$12,520
-
kW-mo/yr
|
$1,660 |
$8,700
-
MMBtu
|
$150 | $100 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs