ITAC Assessment: DS0138
ITAC logo
ITAC Assessment: DS0138
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Molded Plastic and Metal Connectors
NAICS
n/a
SIC 3678: Electronic Connectors
Sales Range $5
M
to 10
M
# of Employees 74
Plant Area 36,000
ft2
Annual Production 280,500
pieces
Production Hrs. Annual 4,810
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,297 1,665,299
kWh
Electricity Demand $41,305 5,484
kW-mo/yr
Electricity Fees $2,138 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $105,141 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $101,938

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,384 $998 $2,181
64,185
kWh
$1,203
-
kW-mo/yr
- -
02 2.2511: Insulate bare equipment $242 $110 $242
7,034
kWh
- - -
03 2.4221: Install compressor air intakes in coolest locations $629 $875 $405
12,016
kWh
$224
-
kW-mo/yr
- -
04 3.4116: Meter recycled water (to reduce sewer charges) $1,273 $400 - - $1,273
-
Tgal
-
05 2.4224: Upgrade controls on compressors $1,165 $241 $580
16,999
kWh
- - $585
06 4.611: Begin a practice of predictive / preventative maintenance $1,688 - - - - $1,688
07 3.2176: Increase use of automation $96,760 $65,000 - - - $96,760
TOTAL RECOMMENDED $105,141 $67,624 $3,408
100,234
kWh
$1,427
-
kW-mo/yr
$1,273
-
Tgal
$99,033
TOTAL IMPLEMENTED $101,938 $67,114 $3,166
93,200
kWh
$1,427
-
kW-mo/yr
- $97,345
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs