| Assessment Year | 1999 |
|---|---|
| Principal Product | Egg Cartons |
| NAICS |
n/a
|
| SIC | 2646: |
| Sales Range | $5 M to 10M |
| # of Employees | 76 |
| Plant Area |
51,600
ft2
|
| Annual Production | 140,000,000
pieces
|
| Production Hrs. Annual | 8,640
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $106,452 | 6,315,651 |
kWh
|
$0.017 |
| Electricity Demand | $98,222 | 10,236 |
kW-mo/yr
|
$9.60 |
| Electricity Fees | $4,717 | - |
|
- |
| Natural Gas | $250,770 | 87,567 |
MMBtu
|
$2.86 |
| LPG | $5,755 | 342 |
MMBtu
|
$16.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,068 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $43,768 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,482 | $5,161 |
$572
33,705
kWh
|
$910
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,120 | $375 |
$625
36,635
kWh
|
$495
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $10,691 | $614 |
$5,991
352,579
kWh
|
$4,700
-
kW-mo/yr
|
- | - | - | |
| 04 | 4.211: Consider use / purchase of bulk materials where possible | $3,151 | $3,300 | - | - | - | - | $3,151 | |
| 05 | 2.7313: Recycle air for heating, ventilation and air conditioning | $28,136 | $65,000 | - | - |
$28,136
-
MMBtu
|
- | - | |
| 06 | 4.423: Move product using mechanical means | $4,180 | $13,250 | - | - | - | $4,180 | - | |
| 07 | 4.821: Pay bills on time to avoid late fees | $308 | - | - | - | - | - | $308 | |
| TOTAL RECOMMENDED | $49,068 | $87,700 |
$7,188
422,919
kWh
|
$6,105
-
kW-mo/yr
|
$28,136
-
MMBtu
|
$4,180 | $3,459 | ||
| TOTAL IMPLEMENTED | $43,768 | $74,075 |
$6,563
386,284
kWh
|
$5,610
-
kW-mo/yr
|
$28,136
-
MMBtu
|
- | $3,459 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs