Assessment Year | 1999 |
---|---|
Principal Product | Quartz Crystals and Frequency Control Components |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
32,000
ft2
|
Annual Production | 5,200
pieces
|
Production Hrs. Annual | 4,368
hrs
|
Location (State) | South Dakota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,489 | 1,881,301 |
kWh
|
$0.029 |
Electricity Demand | $26,479 | 4,044 |
kW-mo/yr
|
$6.55 |
Electricity Fees | $5,327 | - |
|
- |
Natural Gas | $7,193 | 1,448 |
MMBtu
|
$4.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,668 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,037 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,707 | $13,320 |
$3,585
119,578
kWh
|
$2,122
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $330 | $300 |
$204
6,741
kWh
|
$126
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2511: Insulate bare equipment | $883 | $692 | - | - |
$883
-
MMBtu
|
- | - | - | |
04 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,048 | $38 | - | - | - | - |
$1,048
-
lb
|
- | |
05 | 3.4151: Minimize water usage | $655 | $520 | - | - |
$250
-
MMBtu
|
$270
-
Tgal
|
- |
$135
-
Tgal
|
|
06 | 3.4111: Use closed cycle process to minimize waste water production | $7,045 | $20,000 |
$(-2,476.0)
(-79,426)
kWh
|
$(-1,486.0)
-
kW-mo/yr
|
- |
$7,338
-
Tgal
|
- |
$3,669
-
Tgal
|
|
TOTAL RECOMMENDED | $15,668 | $34,870 |
$1,313
46,893
kWh
|
$762
-
kW-mo/yr
|
$1,133
-
MMBtu
|
$7,608
-
Tgal
|
$1,048
-
lb
|
$3,804
-
Tgal
|
||
TOTAL IMPLEMENTED | $6,037 | $13,620 |
$3,789
126,319
kWh
|
$2,248
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs