Assessment Year | 1998 |
---|---|
Principal Product | Precision Granite Bases |
NAICS |
n/a
|
SIC | 3298: |
Sales Range | $5 M to 10M |
# of Employees | 90 |
Plant Area |
68,990
ft2
|
Annual Production | 9,000,000
lb
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,696 | 1,064,771 |
kWh
|
$0.034 |
Electricity Demand | $21,378 | 2,782 |
kW-mo/yr
|
$7.68 |
Electricity Fees | $185 | - |
|
- |
Natural Gas | $8,492 | 1,833 |
MMBtu
|
$4.63 |
LPG | $3,273 | 280 |
MMBtu
|
$11.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $33,852 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,221 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $1,311 | $1,155 | - | - |
$1,311
-
MMBtu
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $240 | $250 |
$152
4,396
kWh
|
$88
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $679 | $50 |
$679
19,930
kWh
|
- | - | - | - | - | - | |
04 | 4.211: Consider use / purchase of bulk materials where possible | $1,620 | $1,350 | - | - | - | - | - | $1,620 | - | |
05 | 3.4154: Eliminate leaks in water lines and valves | $962 | $74 | - | - | - | - | - | - |
$962
-
Tgal
|
|
06 | 3.7135: Minimize use of rags through worker training | $11,700 | $700 | - | - | - | - | - | $11,700 | - | |
07 | 3.1191: Change procedures / equipment / operating conditions | $700 | $6 | - | - | - | - | $700 | - | - | |
08 | 3.1191: Change procedures / equipment / operating conditions | $16,640 | - | - | - | - | $16,640 | - | - | - | |
TOTAL RECOMMENDED | $33,852 | $3,585 |
$831
24,326
kWh
|
$88
-
kW-mo/yr
|
$1,311
-
MMBtu
|
$16,640 | $700 | $13,320 |
$962
-
Tgal
|
||
TOTAL IMPLEMENTED | $19,221 | $380 |
$831
24,326
kWh
|
$88
-
kW-mo/yr
|
- | $16,640 | $700 | - |
$962
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs