ITAC Assessment: DS0114
ITAC logo
ITAC Assessment: DS0114
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Stationary and Transport Tanks
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 67
Plant Area 40,744
ft2
Annual Production 19,760
pieces
Production Hrs. Annual 7,332
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,287 1,156,213
kWh
Electricity Demand $14,643 1,788
kW-mo/yr
Electricity Fees $1,544 -
Natural Gas $16,889 3,205
MMBtu
LPG $10,738 1,046
MMBtu
Fuel Oil #2 $7,222 732
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,972 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,799

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,696 $82 $1,410
42,790
kWh
$286
-
kW-mo/yr
- - - -
02 2.4221: Install compressor air intakes in coolest locations $908 $500 $701
21,102
kWh
$207
-
kW-mo/yr
- - - -
03 4.114: Add/modify equipment to improve drying process $1,443 $278 - - - - - $1,443
04 3.5316: Contract a wood pallet recycling company $410 $150 - - $410
-
lb
- - -
05 3.2121: Convert to electrostatic powder coating $27,855 $12,000 - - - $10,560 - $17,295
06 2.8121: Apply for tax-free status for energy purchases $578 $30 - - - - $578 -
07 2.8123: Pay utility bills on time $82 - - - - - $82 -
TOTAL RECOMMENDED $32,972 $13,040 $2,111
63,892
kWh
$493
-
kW-mo/yr
$410
-
lb
$10,560 $660 $18,738
TOTAL IMPLEMENTED $3,799 $390 $1,410
42,790
kWh
$286
-
kW-mo/yr
- - $660 $1,443
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs