ITAC Assessment: DS0100
ITAC logo
ITAC Assessment: DS0100
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Fixtures and Equipment for the Performing Arts
NAICS
n/a
SIC 2531: Public Building and Related Furniture
Sales Range $10
M
to 50
M
# of Employees 356
Plant Area 260,365
ft2
Annual Production 292,500
pieces
Production Hrs. Annual 4,368
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $84,367 3,058,617
kWh
Electricity Demand $85,925 7,248
kW-mo/yr
Electricity Fees $14,577 -
Natural Gas $19,052 9,125
MMBtu
LPG $8,090 895
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $542,879 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,219

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,501 $7,978 $2,010
71,805
kWh
$2,491
-
kW-mo/yr
- - - - -
02 2.4221: Install compressor air intakes in coolest locations $961 $1,250 $420
14,947
kWh
$541
-
kW-mo/yr
- - - - -
03 2.3132: Recharge batteries on during off-peak demand periods $3,757 $775 - $3,757
-
kW-mo/yr
- - - - -
04 3.8142: Distill contaminated solvents for reuse $1,927 $6,000 $(-474.0)
1,758
kWh
- - $1,537
-
gal
$(-936.0) - $1,800
05 3.5111: Filter and reuse hydraulic oil $300 $160 - - - $300
-
gal
- - -
06 4.211: Consider use / purchase of bulk materials where possible $505 $1,089 - - - - - - $505
07 3.1191: Change procedures / equipment / operating conditions $89,400 - - - - - - - $89,400
08 3.1191: Change procedures / equipment / operating conditions $441,528 $545,000 $(-23,922.0)
(-854,631)
kWh
$(-46,766.0)
-
kW-mo/yr
$(-7,784.0)
-
MMBtu
- - $520,000 -
TOTAL RECOMMENDED $542,879 $562,252 $(-21,966.0)
(-766,121)
kWh
$(-39,977.0)
-
kW-mo/yr
$(-7,784.0)
-
MMBtu
$1,837
-
gal
$(-936.0) $520,000 $91,705
TOTAL IMPLEMENTED $9,219 $10,003 $2,430
86,752
kWh
$6,789
-
kW-mo/yr
- - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs