Assessment Year | 1997 |
---|---|
Principal Product | Processed Grains |
NAICS |
n/a
|
SIC | 2041: Flour and Other Grain Mill Products |
Sales Range | $5 M to 10M |
# of Employees | 44 |
Plant Area |
25,200
ft2
|
Annual Production | 13,500
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | North Dakota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $66,745 | 2,330,012 |
kWh
|
$0.029 |
Electricity Demand | $65,304 | 9,480 |
kW-mo/yr
|
$6.89 |
Electricity Fees | $2,831 | - |
|
- |
Natural Gas | $35,527 | 7,964 |
MMBtu
|
$4.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,180 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,402 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,324 | $7,600 |
$1,348
46,600
kWh
|
$976
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.7124: Make a practice of turning off lights when not needed | $179 | $53 |
$179
6,155
kWh
|
- | - | - | - | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $472 | $750 |
$348
12,016
kWh
|
$124
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.3212: Optimize plant power factor | $1,824 | $2,094 | - | - | $1,824 | - | - | - | - | |
05 | 3.1162: Use less wasteful packaging | $11,890 | $4,000 | - | - | - | - |
$890
-
lb
|
$11,000 | - | |
06 | 2.2511: Insulate bare equipment | $13,509 | $62,000 | - | - | - |
$13,509
-
MMBtu
|
- | - | - | |
07 | 2.8113: Purchase gas directly from a contract gas supplier | $3,982 | $2,500 | - | - | - | - | - | - | $3,982 | |
TOTAL RECOMMENDED | $34,180 | $78,997 |
$1,875
64,771
kWh
|
$1,100
-
kW-mo/yr
|
$1,824 |
$13,509
-
MMBtu
|
$890
-
lb
|
$11,000 | $3,982 | ||
TOTAL IMPLEMENTED | $27,402 | $68,147 |
$179
6,155
kWh
|
- | $1,824 |
$13,509
-
MMBtu
|
$890
-
lb
|
$11,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs