Assessment Year | 1997 |
---|---|
Principal Product | Metal Fabricated Products |
NAICS |
n/a
|
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $1 M to 5M |
# of Employees | 45 |
Plant Area |
95,000
ft2
|
Annual Production | 9,000
ton
|
Production Hrs. Annual | 4,940
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $38,314 | 1,163,540 |
kWh
|
$0.033 |
Electricity Demand | $36,648 | 4,896 |
kW-mo/yr
|
$7.49 |
Electricity Fees | $11,779 | - |
|
- |
Natural Gas | $9,870 | 3,653 |
MMBtu
|
$2.70 |
LPG | $6,594 | 734 |
MMBtu
|
$8.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,350 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,656 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,439 | $2,055 |
$801
24,326
kWh
|
$638
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $327 | $280 |
$255
7,620
kWh
|
$72
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $134 | $182 |
$105
17,292
kWh
|
$29
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $1,905 | $2,100 | - | - |
$1,905
-
MMBtu
|
- | - | - | - | |
05 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $2,123 | $700 | - | - | - |
$341
-
gal
|
- | - | $1,782 | |
06 | 3.7131: Use a rag recycle service | $227 | $750 | - | - | - | - |
$227
-
lb
|
- | - | |
07 | 4.515: Install shelves / racks to utilize unused space | $12,302 | $5,500 | - | - | - | - | - | $12,302 | - | |
08 | 2.8121: Apply for tax-free status for energy purchases | $2,893 | $360 | - | - | - | - | - | $2,893 | - | |
TOTAL RECOMMENDED | $21,350 | $11,927 |
$1,161
49,238
kWh
|
$739
-
kW-mo/yr
|
$1,905
-
MMBtu
|
$341
-
gal
|
$227
-
lb
|
$15,195 | $1,782 | ||
TOTAL IMPLEMENTED | $15,656 | $6,322 |
$360
24,912
kWh
|
$101
-
kW-mo/yr
|
- | - | - | $15,195 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs