Assessment Year | 2003 |
---|---|
Principal Product | pre cast concrete |
NAICS | 327332: Concrete Pipe Manufacturing |
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
n/a
|
Annual Production | 80,000
ton
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,494 | 1,279,680 |
kWh
|
$0.028 |
Electricity Demand | $47,928 | 64,380 |
kW-mo/yr
|
$0.74 |
Electricity Fees | $4,636 | - |
|
- |
Natural Gas | $97,381 | 20,378 |
MMBtu
|
$4.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,536 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,900 | - | n/a | - |
$2,900
-
kW-mo/yr
|
- |
02 | 2.3212: Optimize plant power factor | $5,967 | - | n/a | - |
$5,967
-
kW-mo/yr
|
- |
03 | 2.2135: Repair and eliminate steam leaks | $1,500 | $550 | n/a | - | - |
$1,500
-
MMBtu
|
04 | 2.2437: Recover waste heat from equipment | $2,090 | $886 | n/a | - | - |
$2,090
-
MMBtu
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,079 | $320 | n/a |
$413
13,600
kWh
|
$666
-
kW-mo/yr
|
- |
TOTAL RECOMMENDED | $13,536 | $1,756 |
$413
13,600
kWh
|
$9,533
-
kW-mo/yr
|
$3,590
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs