ITAC Assessment: UU0045
ITAC logo
ITAC Assessment: UU0045
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product pre cast concrete
NAICS 327332: Concrete Pipe Manufacturing
SIC 3272: Concrete Products, Except Block and Brick
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area
n/a
Annual Production 80,000
ton
Production Hrs. Annual 2,600
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,494 1,279,680
kWh
Electricity Demand $47,928 64,380
kW-mo/yr
Electricity Fees $4,636 -
Natural Gas $97,381 20,378
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,536 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,900 - n/a - $2,900
-
kW-mo/yr
-
02 2.3212: Optimize plant power factor $5,967 - n/a - $5,967
-
kW-mo/yr
-
03 2.2135: Repair and eliminate steam leaks $1,500 $550 n/a - - $1,500
-
MMBtu
04 2.2437: Recover waste heat from equipment $2,090 $886 n/a - - $2,090
-
MMBtu
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,079 $320 n/a $413
13,600
kWh
$666
-
kW-mo/yr
-
TOTAL RECOMMENDED $13,536 $1,756 $413
13,600
kWh
$9,533
-
kW-mo/yr
$3,590
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs