| Assessment Year | 2003 |
|---|---|
| Principal Product | pre cast concrete |
| NAICS | 327332: Concrete Pipe Manufacturing |
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 75 |
| Plant Area |
n/a
|
| Annual Production | 80,000
ton
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $35,494 | 1,279,680 |
kWh
|
$0.028 |
| Electricity Demand | $47,928 | 64,380 |
kW-mo/yr
|
$0.74 |
| Electricity Fees | $4,636 | - |
|
- |
| Natural Gas | $97,381 | 20,378 |
MMBtu
|
$4.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $13,536 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,900 | - | n/a | - |
$2,900
-
kW-mo/yr
|
- |
| 02 | 2.3212: Optimize plant power factor | $5,967 | - | n/a | - |
$5,967
-
kW-mo/yr
|
- |
| 03 | 2.2135: Repair and eliminate steam leaks | $1,500 | $550 | n/a | - | - |
$1,500
-
MMBtu
|
| 04 | 2.2437: Recover waste heat from equipment | $2,090 | $886 | n/a | - | - |
$2,090
-
MMBtu
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,079 | $320 | n/a |
$413
13,600
kWh
|
$666
-
kW-mo/yr
|
- |
| TOTAL RECOMMENDED | $13,536 | $1,756 |
$413
13,600
kWh
|
$9,533
-
kW-mo/yr
|
$3,590
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs