Assessment Year | 1997 |
---|---|
Principal Product | Fine Line Computer Components |
NAICS |
n/a
|
SIC | 3231: Glass Products, Made of Purchased Glass |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
116,800
ft2
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 5,200
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $114,092 | 6,421,747 |
kWh
|
$0.018 |
Electricity Demand | $94,685 | 14,076 |
kW-mo/yr
|
$6.73 |
Electricity Fees | $2,237 | - |
|
- |
Natural Gas | $63,908 | 21,825 |
MMBtu
|
$2.93 |
LPG | $14,800 | 1,385 |
MMBtu
|
$10.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $128,759 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $117,929 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $1,097 | $1,800 |
$766
42,497
kWh
|
$331
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,210 | $1,910 | - | - |
$1,692
-
MMBtu
|
$518
-
MMBtu
|
- | - | - | - | - | |
03 | 2.2514: Cover open tanks | $634 | $242 | - | - |
$634
-
MMBtu
|
- | - | - | - | - | - | |
04 | 2.2628: Utilize a less expensive cooling method | $16,937 | $20,000 |
$(-1,092.0)
(-60,668)
kWh
|
$(-853.0)
-
kW-mo/yr
|
- | - |
$13,342
-
Tgal
|
- | - | - |
$5,540
-
Tgal
|
|
05 | 3.6192: Use a less expensive method of waste removal | $10,196 | $32,400 |
$(-405.0)
(-22,567)
kWh
|
$(-3,443.0)
-
kW-mo/yr
|
- | - | - |
$16,384
-
lb
|
$(-2,340.0) | - | - | |
06 | 3.4116: Meter recycled water (to reduce sewer charges) | $13,735 | $9,500 | - | - | - | - |
$13,735
-
Tgal
|
- | - | - | - | |
07 | 2.1335: Replace gasoline with diesel, lpg, or natural gas | $13,750 | $19,000 | - | - | - | - | - | - | - | $13,750 | - | |
08 | 4.514: Re-arrange equipment layout to reduce handling costs | $70,200 | $65,000 | - | - | - | - | - | - | $70,200 | - | - | |
TOTAL RECOMMENDED | $128,759 | $149,852 |
$(-731.0)
(-40,738)
kWh
|
$(-3,965.0)
-
kW-mo/yr
|
$2,326
-
MMBtu
|
$518
-
MMBtu
|
$27,077
-
Tgal
|
$16,384
-
lb
|
$67,860 | $13,750 |
$5,540
-
Tgal
|
||
TOTAL IMPLEMENTED | $117,929 | $117,210 |
$(-326.0)
(-18,171)
kWh
|
$(-522.0)
-
kW-mo/yr
|
$1,692
-
MMBtu
|
$518
-
MMBtu
|
$27,077
-
Tgal
|
- | $70,200 | $13,750 |
$5,540
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs