ITAC Assessment: CO0561
ITAC logo
ITAC Assessment: CO0561
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Architectural millwork and fixtures
NAICS 337215: Showcase, Partition, Shelving, and Locker Manufacturing
SIC 2426: Hardwood Dimension and Flooring Mills
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 86,700
ft2
Annual Production 195
pieces
Production Hrs. Annual 2,860
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,787 905,520
kWh
Electricity Demand $49,016 3,909
kW-mo/yr
Electricity Fees $480 -
Natural Gas $16,754 1,988
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,750 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2437: Recover waste heat from equipment $2,890 $4,100 - - $2,890
-
MMBtu
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,380 $270 $460
12,700
kWh
$920
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $700 $2,760 $230
6,500
kWh
$470
-
kW-mo/yr
- - -
04 2.2711: Utilize outside air instead of conditioned air for drying $240 $480 $80
2,200
kWh
$160
-
kW-mo/yr
- - -
05 2.7145: Install skylights $10,440 $90,000 $3,890
107,600
kWh
$6,020
-
kW-mo/yr
- $200 $330
06 2.7142: Utilize higher efficiency lamps and/or ballasts $8,460 $29,920 $2,590
71,800
kWh
$4,120
-
kW-mo/yr
- $680 $1,070
07 2.7135: Install occupancy sensors $640 $960 $560
15,600
kWh
- - $30 $50
TOTAL RECOMMENDED $24,750 $128,490 $7,810
216,400
kWh
$11,690
-
kW-mo/yr
$2,890
-
MMBtu
$910 $1,450
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs