Assessment Year | 1997 |
---|---|
Principal Product | Plastic Bags |
NAICS |
n/a
|
SIC | 2673: Plastics, Foil, and Coated Paper Bags |
Sales Range | $10 M to 50M |
# of Employees | 295 |
Plant Area |
232,110
ft2
|
Annual Production | 79,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | South Dakota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $719,178 | 24,518,758 |
kWh
|
$0.029 |
Electricity Demand | $267,283 | 38,196 |
kW-mo/yr
|
$7.00 |
Electricity Fees | $59,511 | - |
|
- |
Natural Gas | $62,003 | 14,863 |
MMBtu
|
$4.17 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $822,407 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,148 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $3,806 | $28,425 |
$2,593
88,511
kWh
|
$1,213
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $4,342 | $750 |
$4,342
148,300
kWh
|
- | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,866 | $17,925 |
$7,338
250,586
kWh
|
$2,528
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2511: Insulate bare equipment | $14,716 | $19,230 |
$13,456
459,261
kWh
|
$1,260
-
kW-mo/yr
|
- | - | - | - | |
05 | 3.5316: Contract a wood pallet recycling company | $1,360 | $100 | - | - | - | - | $1,360 | - | |
06 | 3.2176: Increase use of automation | $752,148 | $810,000 |
$(-24,732.0)
(-575,029)
kWh
|
- | - | $776,880 | - | - | |
07 | 3.5311: Recover and reuse waste material | $36,169 | - | - | - |
$576
-
lb
|
$(-2,800.0) | - | $38,393 | |
TOTAL RECOMMENDED | $822,407 | $876,430 |
$2,997
371,629
kWh
|
$5,001
-
kW-mo/yr
|
$576
-
lb
|
$774,080 | $1,360 | $38,393 | ||
TOTAL IMPLEMENTED | $8,148 | $29,175 |
$6,935
236,811
kWh
|
$1,213
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs