| Assessment Year | 1996 |
|---|---|
| Principal Product | Polyethylene and Fiberglass Tanks |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 70 |
| Plant Area |
113,000
ft2
|
| Annual Production | 60,000
pieces
|
| Production Hrs. Annual | 4,472
hrs
|
| Location (State) | South Dakota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $53,497 | 1,745,311 |
kWh
|
$0.031 |
| Electricity Demand | $51,228 | 6,984 |
kW-mo/yr
|
$7.34 |
| Electricity Fees | $8,772 | - |
|
- |
| Natural Gas | $41,999 | 11,994 |
MMBtu
|
$3.50 |
| LPG | $64,904 | 9,525 |
MMBtu
|
$6.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $41,971 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $20,857 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $2,348 | $1,700 | - | - | $2,348 | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,487 | $21,753 |
$3,232
104,338
kWh
|
$2,255
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,576 | $8,500 |
$643
20,809
kWh
|
- | - |
$7,933
-
MMBtu
|
- | |
| 04 | 3.1175: Use a different or recycled raw material | $21,114 | - | - | - | - | - |
$21,114
-
lb
|
|
| 05 | 2.6232: Install set-back timers | $2,926 | $150 | - | - | - |
$2,926
-
MMBtu
|
- | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,520 | - | - | - | - |
$1,520
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $41,971 | $32,103 |
$3,875
125,147
kWh
|
$2,255
-
kW-mo/yr
|
$2,348 |
$12,379
-
MMBtu
|
$21,114
-
lb
|
||
| TOTAL IMPLEMENTED | $20,857 | $32,103 |
$3,875
125,147
kWh
|
$2,255
-
kW-mo/yr
|
$2,348 |
$12,379
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs