Assessment Year | 1996 |
---|---|
Principal Product | Computers and Circuit Boards |
NAICS |
n/a
|
SIC | 3571: Electronic Computers |
Sales Range | $1 M to 5M |
# of Employees | 482 |
Plant Area |
262,340
ft2
|
Annual Production | 174
thousand feet
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $827,171 | 19,313,306 |
kWh
|
$0.043 |
Natural Gas | $81,133 | 15,319 |
MMBtu
|
$5.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,395 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,958 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,865 | $9,854 |
$3,865
89,977
kWh
|
- | - | - | |
02 | 3.4114: Replace city water with recycled water via cooling tower | $8,572 | $42,350 | - |
$4,178
-
Tgal
|
- |
$4,394
-
Tgal
|
|
03 | 2.8113: Purchase gas directly from a contract gas supplier | $12,255 | - | - | - | $12,255 | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $2,703 | $750 |
$2,703
63,013
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $27,395 | $52,954 |
$6,568
152,990
kWh
|
$4,178
-
Tgal
|
$12,255 |
$4,394
-
Tgal
|
||
TOTAL IMPLEMENTED | $14,958 | $750 |
$2,703
63,013
kWh
|
- | $12,255 | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs