Assessment Year | 1996 |
---|---|
Principal Product | Heat Conductive Material & Circuit Board Plates |
NAICS |
n/a
|
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
55,000
ft2
|
Annual Production | 563,200
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $101,606 | 3,278,429 |
kWh
|
$0.031 |
Electricity Demand | $65,971 | 10,325 |
kW-mo/yr
|
$6.39 |
Electricity Fees | $5,730 | - |
|
- |
Natural Gas | $199,893 | 90,663 |
MMBtu
|
$2.20 |
LPG | $7,500 | 1,380 |
MMBtu
|
$5.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,868 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $66,868 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $3,012 | $6,282 |
$1,848
59,496
kWh
|
$1,164
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,752 | $14,574 |
$3,578
115,475
kWh
|
$2,174
-
kW-mo/yr
|
- | - | |
03 | 2.7135: Install occupancy sensors | $483 | $1,200 |
$483
15,533
kWh
|
- | - | - | |
04 | 2.4224: Upgrade controls on compressors | $629 | $20 |
$288
7,327
kWh
|
- |
$341
-
MMBtu
|
- | |
05 | 2.2443: Re-use or recycle hot or cold process exhaust air | $25,792 | $80,000 |
$(-3,615.0)
(-81,477)
kWh
|
- |
$29,407
-
MMBtu
|
- | |
06 | 3.1175: Use a different or recycled raw material | $31,200 | - | - | - | - |
$31,200
-
lb
|
|
TOTAL RECOMMENDED | $66,868 | $102,076 |
$2,582
116,354
kWh
|
$3,338
-
kW-mo/yr
|
$29,748
-
MMBtu
|
$31,200
-
lb
|
||
TOTAL IMPLEMENTED | $66,868 | $102,076 |
$2,582
116,354
kWh
|
$3,338
-
kW-mo/yr
|
$29,748
-
MMBtu
|
$31,200
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs