Assessment Year | 2016 |
---|---|
Principal Product | Sporting Goods Handles |
NAICS | 321999: All Other Miscellaneous Wood Product Manufacturing |
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 85 |
Plant Area |
55,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $50,545 | 624,200 |
kWh
|
$0.081 |
Electricity Demand | $26,193 | 1,866 |
kW-mo/yr
|
$14.04 |
Electricity Fees | $408 | - |
|
- |
Natural Gas | $12,261 | 1,900 |
MMBtu
|
$6.45 |
LPG | $882 | 36 |
MMBtu
|
$24.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $118,822 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $581 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $14,385 | $50,000 |
$29,089
359,125
kWh
|
$27,378
-
kW-mo/yr
|
$(-40,082.0)
-
MMBtu
|
- | $(-2,000.0) | - | - | |
02 | 2.7135: Install occupancy sensors | $3,494 | $825 |
$1,398
17,263
kWh
|
$2,096
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,448 | $20 |
$747
9,218
kWh
|
$701
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,019 | $2,552 |
$525
6,484
kWh
|
$494
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.8227: Adjust / maintain fork lift trucks for most efficient operation | $658 | $1,225 | - | - |
$(-224.0)
-
MMBtu
|
$882
-
MMBtu
|
- | - | - | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $581 | $2,500 |
$(-119.0)
(-1,473)
kWh
|
$(-84.0)
-
kW-mo/yr
|
$784
-
MMBtu
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $437 | $748 |
$195
2,408
kWh
|
$184
-
kW-mo/yr
|
- | - | $28 | - | $30 | |
08 | 3.1182: Make a new by-product | $96,800 | $50,000 | - | - | - | - | - | $96,800 | - | |
TOTAL RECOMMENDED | $118,822 | $107,870 |
$31,835
393,025
kWh
|
$30,769
-
kW-mo/yr
|
$(-39,522.0)
-
MMBtu
|
$882
-
MMBtu
|
$(-1,972.0) | $96,800 | $30 | ||
TOTAL IMPLEMENTED | $581 | $2,500 |
$(-119.0)
(-1,473)
kWh
|
$(-84.0)
-
kW-mo/yr
|
$784
-
MMBtu
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs