ITAC Assessment: OR0095
ITAC logo
ITAC Assessment: OR0095
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product RADIAL SAW BLADES
NAICS
n/a
SIC 3425: Saw Blades and Handsaws
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area
n/a
Annual Production 2,200,000
pieces
Production Hrs. Annual 6,120
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $132,327 2,786,929
kWh
Natural Gas $14,854 2,885
MMBtu
LPG $6,055 652
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,785 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,099

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $658 $465 $718
15,826
kWh
$(-60.0)
02 2.2511: Insulate bare equipment $2,105 $2,035 $2,105
55,100
kWh
-
03 2.4133: Use most efficient type of electric motors $336 $345 $336
7,327
kWh
-
04 2.3212: Optimize plant power factor $390 $1,050 $390
-
kWh
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $296 $1,325 $296
6,448
kWh
-
TOTAL RECOMMENDED $3,785 $5,220 $3,845
84,701
kWh
$(-60.0)
TOTAL IMPLEMENTED $3,099 $2,845 $3,159
78,253
kWh
$(-60.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs