ITAC Assessment: DS0033
ITAC logo
ITAC Assessment: DS0033
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Beef patties, meat snacks, sausage products
NAICS
n/a
SIC 2011: Meat Packing Plants
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 75,825
ft2
Annual Production 25,000,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $185,431 3,579,426
kWh
LPG $59,811 15,388
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,935 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,635

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $3,602 $2,709 $3,602
79,132
kWh
-
02 2.4133: Use most efficient type of electric motors $5,911 $8,264 $5,911
93,787
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $631 $300 $631
19,637
kWh
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,479 $2,413 $2,479
58,324
kWh
-
05 2.2511: Insulate bare equipment $1,377 $104 - $1,377
-
MMBtu
06 2.2511: Insulate bare equipment $122 $112 - $122
-
MMBtu
07 2.2511: Insulate bare equipment $1,492 $3,107 - $1,492
-
MMBtu
08 2.2511: Insulate bare equipment $850 $284 $850
25,498
kWh
-
09 2.8114: Change rate schedules or other changes in utility service $30,890 $268,600 $30,890
-
kWh
-
10 2.2437: Recover waste heat from equipment $6,581 $16,000 - $6,581
-
MMBtu
TOTAL RECOMMENDED $53,935 $301,893 $44,363
276,378
kWh
$9,572
-
MMBtu
TOTAL IMPLEMENTED $9,635 $11,085 $9,513
172,919
kWh
$122
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs