Assessment Year | 1995 |
---|---|
Principal Product | Beef patties, meat snacks, sausage products |
NAICS |
n/a
|
SIC | 2011: Meat Packing Plants |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
75,825
ft2
|
Annual Production | 25,000,000
lb
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $185,431 | 3,579,426 |
kWh
|
$0.052 |
LPG | $59,811 | 15,388 |
MMBtu
|
$3.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $53,935 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,635 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,602 | $2,709 |
$3,602
79,132
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $5,911 | $8,264 |
$5,911
93,787
kWh
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $631 | $300 |
$631
19,637
kWh
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,479 | $2,413 |
$2,479
58,324
kWh
|
- | |
05 | 2.2511: Insulate bare equipment | $1,377 | $104 | - |
$1,377
-
MMBtu
|
|
06 | 2.2511: Insulate bare equipment | $122 | $112 | - |
$122
-
MMBtu
|
|
07 | 2.2511: Insulate bare equipment | $1,492 | $3,107 | - |
$1,492
-
MMBtu
|
|
08 | 2.2511: Insulate bare equipment | $850 | $284 |
$850
25,498
kWh
|
- | |
09 | 2.8114: Change rate schedules or other changes in utility service | $30,890 | $268,600 |
$30,890
-
kWh
|
- | |
10 | 2.2437: Recover waste heat from equipment | $6,581 | $16,000 | - |
$6,581
-
MMBtu
|
|
TOTAL RECOMMENDED | $53,935 | $301,893 |
$44,363
276,378
kWh
|
$9,572
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,635 | $11,085 |
$9,513
172,919
kWh
|
$122
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs