ITAC Assessment: DS0030
ITAC logo
ITAC Assessment: DS0030
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Folding Cartons
NAICS
n/a
SIC 2657: Folding Paperboard Boxes, Including Sanitary
Sales Range $10
M
to 50
M
# of Employees 85
Plant Area 164,076
ft2
Annual Production 23,000,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $171,771 2,691,090
kWh
Natural Gas $32,182 7,770
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,813 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $14,132 $19,273 $14,132
230,657
kWh
-
02 2.7135: Install occupancy sensors $237 $431 $237
6,741
kWh
-
03 2.4133: Use most efficient type of electric motors $2,645 $3,448 $2,645
37,222
kWh
-
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,686 $80 $1,686
48,652
kWh
-
05 2.2511: Insulate bare equipment $97 $69 - $97
-
MMBtu
06 2.4221: Install compressor air intakes in coolest locations $604 $420 $604
16,706
kWh
-
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $412 $650 $412
7,620
kWh
-
TOTAL RECOMMENDED $19,813 $24,371 $19,716
347,598
kWh
$97
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs