ITAC Assessment: DL0250
ITAC logo
ITAC Assessment: DL0250
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Asphalt
NAICS 324121: Asphalt Paving Mixture and Block Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 16,000
ft2
Annual Production 900,000
ton
Production Hrs. Annual 4,181
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $240,950 1,512,314
kWh
Electricity Demand $33,657 6,747
kW-mo/yr
Electricity Fees $4,450 -
Natural Gas $573,950 114,790
MMBtu
TOTAL YEARLY COSTS $853,007
RECOMMENDED SAVINGS* $147,048 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4224: Upgrade controls on compressors $5,277 $4,500 $4,610
28,995
kWh
$667
-
kW-mo/yr
-
02 2.4224: Upgrade controls on compressors $42,985 $31,000 $37,554
236,190
kWh
$5,431
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $25,468 $16,000 $22,250
139,935
kWh
$3,218
-
kW-mo/yr
-
04 2.2511: Insulate bare equipment $50,005 $5,100 - - $50,005
-
MMBtu
05 2.4322: Use or replace with energy efficient substitutes $4,948 $18,000 $4,323
27,186
kWh
$625
-
kW-mo/yr
-
06 2.1221: Replace obsolete burners with more efficient ones $18,365 $50,000 - - $18,365
-
MMBtu
TOTAL RECOMMENDED $147,048 $124,600 $68,737
432,306
kWh
$9,941
-
kW-mo/yr
$68,370
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs