Assessment Year | 2024 |
---|---|
Principal Product | Corrugated Paper |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 154 |
Plant Area |
215,000
ft2
|
Annual Production | 634,000
thousand feet
|
Production Hrs. Annual | 6,400
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $714,467 | 6,069,577 |
kWh
|
$0.12 | |
Electricity Demand | $180,581 | 11,785 |
kW-mo/yr
|
$15.32 | |
Electricity Fees | $5,965 | - |
|
- | |
Natural Gas | $393,363 | 57,744 |
MMBtu
|
$6.81 | |
Waste Disposal Costs | |||||
Water Usage | $72,887 | 5,681 |
Tgal
|
$12.83 | |
TOTAL YEARLY COSTS | $1,367,263 | ||||
RECOMMENDED SAVINGS* | $449,475 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2127: Flash condensate to produce lower pressure steam | $6,357 | $1,000 | - |
$5,421
-
MMBtu
|
$936
-
Tgal
|
- | |
02 | 2.4226: Use / purchase optimum sized compressor | $6,768 | - |
$6,768
57,352
kWh
|
- | - | - | |
03 | 2.6218: Turn off equipment when not in use | $22,165 | $5,000 |
$22,165
187,840
kWh
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $52,278 | $20,000 |
$52,278
443,034
kWh
|
- | - | - | |
05 | 3.4155: Meter waste water | $7,907 | $2,000 | - | - | - | $7,907 | |
06 | 2.9114: Use solar heat to make electricty | $354,000 | $3,000,000 |
$354,000
3,000,000
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $449,475 | $3,028,000 |
$435,211
3,688,226
kWh
|
$5,421
-
MMBtu
|
$936
-
Tgal
|
$7,907 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs