Assessment Year | 2023 |
---|---|
Principal Product | Optical fiber and optoelectronic devices |
NAICS | 334413: Semiconductor and Related Device Manufacturing |
SIC | 3674: Semiconductors and Related Devices |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
166,000
ft2
|
Annual Production | 2,257,288
units
|
Production Hrs. Annual | 4,450
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $879,344 | 6,380,263 |
kWh
|
$0.14 |
Electricity Demand | $98,516 | 13,019 |
kW-mo/yr
|
$7.57 |
Electricity Fees | $176 | - |
|
- |
Natural Gas | $65,526 | 5,592 |
MMBtu
|
$11.72 |
TOTAL YEARLY COSTS | $1,043,562 | |||
RECOMMENDED SAVINGS* | $164,668 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $96,454 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6231: Utilize controls to operate equipment only when needed | $84,324 | - |
$84,324
551,140
kWh
|
- | |
02 | 2.2211: Use optimum temperature | $6,980 | - |
$6,980
45,620
kWh
|
- | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $4,020 | - | - |
$4,020
-
MMBtu
|
|
04 | 2.6231: Utilize controls to operate equipment only when needed | $10,928 | - |
$5,349
34,962
kWh
|
$5,579
-
MMBtu
|
|
05 | 2.6231: Utilize controls to operate equipment only when needed | $16,704 | - |
$16,704
109,178
kWh
|
- | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $14,418 | - |
$14,418
94,233
kWh
|
- | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $3,578 | - |
$3,578
23,383
kWh
|
- | |
08 | 2.4239: Eliminate or reduce compressed air usage | $4,694 | - |
$4,694
30,681
kWh
|
- | |
09 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $6,332 | $20,000 |
$6,332
41,384
kWh
|
- | |
10 | 2.2437: Recover waste heat from equipment | $6,153 | $9,740 | - |
$6,153
-
MMBtu
|
|
11 | 2.2437: Recover waste heat from equipment | $1,387 | $6,500 | - |
$1,387
-
MMBtu
|
|
12 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,150 | $8,994 |
$5,150
33,660
kWh
|
- | |
TOTAL RECOMMENDED | $164,668 | $45,234 |
$147,529
964,241
kWh
|
$17,139
-
MMBtu
|
||
TOTAL IMPLEMENTED | $96,454 | $8,994 |
$96,454
630,420
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs