Assessment Year | 2023 |
---|---|
Principal Product | Carbonated beverages |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $50 M to 100M |
# of Employees | 90 |
Plant Area |
100,000
ft2
|
Annual Production | 30,607
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $241,977 | 4,646,411 |
kWh
|
$0.052 | |
Electricity Demand | $36,061 | 9,590 |
kW-mo/yr
|
$3.76 | |
Electricity Fees | $4,457 | - |
|
- | |
Natural Gas | $79,726 | 17,664 |
MMBtu
|
$4.51 | |
Waste Disposal Costs | |||||
Water Usage | $1,317,555 | 76,115 |
Tgal
|
$17.31 | |
TOTAL YEARLY COSTS | $1,679,776 | ||||
RECOMMENDED SAVINGS* | $90,374 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $28,671 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7229: Air condition only space necessary | $496 | - |
$430
8,271
kWh
|
$66
-
kW-mo/yr
|
- | - | |
02 | 2.7444: Close holes and openings in building such as broken windows | $922 | $520 | - | - |
$922
-
MMBtu
|
- | |
03 | 2.6242: Minimize operation of equipment maintained in standby condition | $6,246 | $4,000 |
$238
4,578
kWh
|
$37
-
kW-mo/yr
|
$5,971
-
MMBtu
|
- | |
04 | 2.6242: Minimize operation of equipment maintained in standby condition | $5,827 | - |
$5,827
97,119
kWh
|
- | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,974 | $10,600 |
$6,044
116,237
kWh
|
$930
-
kW-mo/yr
|
- | - | |
06 | 2.2314: Replace heat treating oven with more efficient unit | $11,196 | $50,000 | - | - |
$11,196
-
MMBtu
|
- | |
07 | 2.2491: Use cooling air which cools hot work pieces for space heating | $2,856 | $16,145 | - | - |
$2,856
-
MMBtu
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,178 | $10,128 |
$3,621
69,642
kWh
|
$557
-
kW-mo/yr
|
- | - | |
09 | 3.4114: Replace city water with recycled water via cooling tower | $51,679 | $50,000 | - | - | - |
$51,679
-
Tgal
|
|
TOTAL RECOMMENDED | $90,374 | $141,393 |
$16,160
295,847
kWh
|
$1,590
-
kW-mo/yr
|
$20,945
-
MMBtu
|
$51,679
-
Tgal
|
||
TOTAL IMPLEMENTED | $28,671 | $70,728 |
$15,922
291,269
kWh
|
$1,553
-
kW-mo/yr
|
$11,196
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs