Assessment Year | 2021 |
---|---|
Principal Product | Diamond Products |
NAICS | 334413: Semiconductor and Related Device Manufacturing |
SIC | 3674: Semiconductors and Related Devices |
Sales Range | $1 M to 5M |
# of Employees | 22 |
Plant Area |
18,000
ft2
|
Annual Production | 2,500
units
|
Production Hrs. Annual | 3,000
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $89,754 | 1,170,134 |
kWh
|
$0.077 | |
Electricity Demand | $13,800 | 2,408 |
kW-mo/yr
|
$5.73 | |
Electricity Fees | $1,800 | - |
|
- | |
Waste Disposal Costs | |||||
Water Usage | $1 | 1 |
Tgal
|
$1.00 | |
TOTAL YEARLY COSTS | $105,355 | ||||
RECOMMENDED SAVINGS* | $7,985 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $5,334 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
---|---|---|---|---|---|
01 | 2.6231: Utilize controls to operate equipment only when needed | $180 | - |
$180
2,334
kWh
|
|
02 | 2.6231: Utilize controls to operate equipment only when needed | $2,910 | - |
$2,910
33,040
kWh
|
|
03 | 2.6231: Utilize controls to operate equipment only when needed | $324 | $50 |
$324
3,676
kWh
|
|
04 | 2.7224: Reduce space conditioning during non-working hours | $1,650 | - |
$1,650
21,400
kWh
|
|
05 | 2.4322: Use or replace with energy efficient substitutes | $361 | $1,200 |
$361
4,100
kWh
|
|
06 | 2.6218: Turn off equipment when not in use | $270 | - |
$270
3,496
kWh
|
|
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $560 | $550 |
$560
6,360
kWh
|
|
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,730 | $2,453 |
$1,730
19,700
kWh
|
|
TOTAL RECOMMENDED | $7,985 | $4,253 |
$7,985
94,106
kWh
|
||
TOTAL IMPLEMENTED | $5,334 | $50 |
$5,334
63,946
kWh
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs