Assessment Year | 2020 |
---|---|
Principal Product | Plastic Films and Resin |
NAICS | 325211: Plastics Material and Resin Manufacturing |
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $10 M to 50M |
# of Employees | 104 |
Plant Area |
180,000
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $870,384 | 13,167,928 |
kWh
|
$0.066 | |
Electricity Demand | $124,702 | 29,191 |
kW-mo/yr
|
$4.27 | |
Electricity Fees | $8,267 | - |
|
- | |
Natural Gas | $194,335 | 37,340 |
MMBtu
|
$5.20 | |
Waste Disposal Costs | |||||
Water Usage | $3,596 | 456 |
Tgal
|
$7.89 | |
TOTAL YEARLY COSTS | $1,201,284 | ||||
RECOMMENDED SAVINGS* | $99,037 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $31,845 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $5,702 | - |
$5,702
86,400
kWh
|
- | |
02 | 2.4226: Use / purchase optimum sized compressor | $22,300 | $15,661 |
$22,300
294,000
kWh
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $41,700 | $6,337 |
$41,700
548,000
kWh
|
- | |
04 | 2.2437: Recover waste heat from equipment | $2,170 | $4,250 | - |
$2,170
-
MMBtu
|
|
05 | 2.7243: Improve air circulation with destratification fans / other methods | $9,500 | $1,400 |
$3,700
48,500
kWh
|
$5,800
-
MMBtu
|
|
06 | 2.2511: Insulate bare equipment | $4,400 | $4,750 | - |
$4,400
-
MMBtu
|
|
07 | 2.2511: Insulate bare equipment | $800 | $95 | - |
$800
-
MMBtu
|
|
08 | 2.2511: Insulate bare equipment | $2,680 | $152 | - |
$2,680
-
MMBtu
|
|
09 | 2.5112: Use continuous equipment which retains process heating conveyors within the heated chamber | $240 | $40 |
$240
3,120
kWh
|
- | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,390 | $3,079 |
$7,390
97,200
kWh
|
- | |
11 | 2.7314: Reduce ventilation air | $940 | - |
$940
12,370
kWh
|
- | |
12 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,215 | $400 |
$1,215
16,000
kWh
|
- | |
TOTAL RECOMMENDED | $99,037 | $36,164 |
$83,187
1,105,590
kWh
|
$15,850
-
MMBtu
|
||
TOTAL IMPLEMENTED | $31,845 | $19,140 |
$31,845
419,570
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs