ITAC Assessment: GT0918
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Ice Cream
NAICS 311520: Ice Cream and Frozen Dessert Manufacturing
SIC 2024: Ice Cream and Frozen Desserts
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area 22,000
ft2
Annual Production 873,600
units
Production Hrs. Annual 2,600
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $145,930 1,456,440
kWh
Natural Gas $22,909 3,882
MMBtu
TOTAL YEARLY COSTS $168,839
RECOMMENDED SAVINGS* $69,730 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,035

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
01 4.821: Pay bills on time to avoid late fees $3,016 $1,488 - $3,016 -
02 2.4231: Reduce the pressure of compressed air to the minimum required $4,414 $3,500 $4,414
44,138
kWh
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,373 $5,449 $3,373
33,726
kWh
- -
04 2.2626: Avoid frost formation on evaporators $47,297 $90,000 $47,297
410,969
kWh
- -
05 2.2211: Use optimum temperature $8,768 $23,162 - - $8,768
-
MMBtu
06 2.1233: Analyze flue gas for proper air/fuel ratio $232 $1,000 - - $232
-
MMBtu
07 2.2121: Increase amount of condensate returned $2,630 $13,862 - - $2,630
-
MMBtu
TOTAL RECOMMENDED $69,730 $138,461 $55,084
488,833
kWh
$3,016 $11,630
-
MMBtu
TOTAL IMPLEMENTED $11,035 $11,437 $7,787
77,864
kWh
$3,016 $232
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs