ITAC Assessment: AS0112
ITAC logo
ITAC Assessment: AS0112
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Fluid Milk
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $100
M
to 500
M
# of Employees 120
Plant Area 56,500
ft2
Annual Production 12,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $811,934 11,587,632
kWh
Natural Gas $133,683 31,557
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $181,882 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,953

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,087 $15,256 $11,087
158,265
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,310 $37,932 $14,310
204,279
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,174 $9,280 $4,174
59,496
kWh
-
04 2.7135: Install occupancy sensors $1,508 $525 $1,508
21,395
kWh
-
05 2.7134: Use photocell controls $1,035 $400 $1,035
14,654
kWh
-
06 2.1233: Analyze flue gas for proper air/fuel ratio $1,694 $4,000 - $1,694
-
MMBtu
07 2.2414: Use waste heat from hot flue gases to preheat $4,941 $16,000 - $4,941
-
MMBtu
08 2.1243: Use heat from boiler blowdown to preheat boiler feed water $2,341 $7,000 - $2,341
-
MMBtu
09 2.2135: Repair and eliminate steam leaks $305 $400 - $305
-
MMBtu
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,970 $700 $2,970
42,497
kWh
-
11 2.4231: Reduce the pressure of compressed air to the minimum required $1,886 - $1,886
26,964
kWh
-
12 2.4314: Use synthetic lubricant $4,287 $4,235 $4,287
48,066
kWh
-
13 2.4133: Use most efficient type of electric motors $11,104 $16,099 $11,104
158,558
kWh
-
14 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,107 - $1,107
15,826
kWh
-
15 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $119,133 $463,200 $157,664
3,382,474
kWh
$(-38,531.0)
-
MMBtu
TOTAL RECOMMENDED $181,882 $575,027 $211,132
4,132,474
kWh
$(-29,250.0)
-
MMBtu
TOTAL IMPLEMENTED $45,953 $81,787 $41,613
594,079
kWh
$4,340
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs