Assessment Year | 2016 |
---|---|
Principal Product | Coffee Packets |
NAICS | 311920: Coffee and Tea Manufacturing |
SIC | 2095: Roasted Coffee |
Sales Range | $500 k to 1M |
# of Employees | 200 |
Plant Area |
200,000
ft2
|
Annual Production | 1,000,000
units
|
Production Hrs. Annual | 7,752
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $696,487 | 8,497,913 |
kWh
|
$0.082 | |
Natural Gas | $11,594 | 1,527 |
MMBtu
|
$7.59 | |
Waste Disposal Costs | |||||
Water Usage | $10,609 | 666 |
Tgal
|
$15.92 | |
Water Disposal | $4,916 | 598 |
Tgal
|
$8.22 | |
TOTAL YEARLY COSTS | $723,606 | ||||
RECOMMENDED SAVINGS* | $139,755 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $3,910 | $200 |
$1,160
14,130
kWh
|
$2,750
-
MMBtu
|
- | - | |
02 | 2.6218: Turn off equipment when not in use | $2,380 | $200 |
$2,380
29,060
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,120 | $1,000 |
$5,120
62,410
kWh
|
- | - | - | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $67,220 | $62,600 |
$67,220
819,800
kWh
|
- | - | - | |
05 | 3.4154: Eliminate leaks in water lines and valves | $4,520 | $6,800 | - | - |
$2,980
-
Tgal
|
$1,540
-
Tgal
|
|
06 | 2.6231: Utilize controls to operate equipment only when needed | $4,385 | $7,400 |
$1,055
12,860
kWh
|
$3,330
-
MMBtu
|
- | - | |
07 | 2.7224: Reduce space conditioning during non-working hours | $2,320 | $4,980 |
$360
4,380
kWh
|
$1,960
-
MMBtu
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $22,000 | $67,370 |
$22,000
268,300
kWh
|
- | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $27,900 | $190,600 |
$27,900
340,270
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $139,755 | $341,150 |
$127,195
1,551,210
kWh
|
$8,040
-
MMBtu
|
$2,980
-
Tgal
|
$1,540
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Usage Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs