ITAC Assessment: AM0034
ITAC logo
ITAC Assessment: AM0034
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product FRUIT CAKES
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $1
M
to 5
M
# of Employees 80
Plant Area
n/a
Annual Production 360,000
lb
Production Hrs. Annual 2,620
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $12,857 220,106
kWh
Natural Gas $4,632 916
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $729 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $625

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.6232: Install set-back timers $275 - $275
9,672
kWh
-
02 2.6214: Shut off pilots in standby equipment $221 $940 - $221
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $27 $23 $27
586
kWh
-
04 2.8112: Combine utility meters $102 $301 - $102
-
MMBtu
05 2.2511: Insulate bare equipment $104 $37 $27
879
kWh
$77
-
MMBtu
TOTAL RECOMMENDED $729 $1,301 $329
11,137
kWh
$400
-
MMBtu
TOTAL IMPLEMENTED $625 $1,264 $302
10,258
kWh
$323
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs