Assessment Year | 2016 |
---|---|
Principal Product | Treated Water |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $5 M to 10M |
# of Employees | 30 |
Plant Area |
100,000
ft2
|
Annual Production | 2,055,250
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $542,732 | 9,687,681 |
kWh
|
$0.056 |
Natural Gas | $7,006 | 1,281 |
MMBtu
|
$5.47 |
TOTAL YEARLY COSTS | $549,738 | |||
RECOMMENDED SAVINGS* | $23,771 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,008 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,622 | $1,000 |
$2,622
46,820
kWh
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,190 | $1,000 |
$9,190
164,086
kWh
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $920 | $6,285 |
$920
16,350
kWh
|
- | |
04 | 2.6231: Utilize controls to operate equipment only when needed | $3,410 | $1,235 |
$3,410
60,970
kWh
|
- | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $366 | $253 |
$366
6,530
kWh
|
- | |
06 | 2.6232: Install set-back timers | $2,512 | $253 |
$510
9,120
kWh
|
$2,002
-
MMBtu
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $163 | - |
$28
492
kWh
|
$135
-
MMBtu
|
|
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $940 | $3,431 |
$940
16,820
kWh
|
- | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,618 | $11,052 |
$1,618
28,894
kWh
|
- | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,030 | $8,740 |
$2,030
36,270
kWh
|
- | |
TOTAL RECOMMENDED | $23,771 | $33,249 |
$21,634
386,352
kWh
|
$2,137
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,008 | $31,014 |
$9,006
160,804
kWh
|
$2,002
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs