Assessment Year | 2015 |
---|---|
Principal Product | EPDM Rubber Membranes |
NAICS | 324122: Asphalt Shingle and Coating Materials Manufacturing |
SIC | 2952: Asphalt Felts and Coatings |
Sales Range | $100 M to 500M |
# of Employees | 250 |
Plant Area |
350,000
ft2
|
Annual Production | 393,000
thousand feet
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,072,735 | 32,032,000 |
kWh
|
$0.065 |
Electricity Demand | $103,806 | 29,555 |
kW-mo/yr
|
$3.51 |
Natural Gas | $310,063 | 50,845 |
MMBtu
|
$6.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $198,990 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $118,160 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $49,150 | $85,250 |
$(-13,330.0)
(-205,150)
kWh
|
$(-1,570.0)
-
kW-mo/yr
|
$64,050
-
MMBtu
|
|
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $9,300 | $34,100 | - | - |
$9,300
-
MMBtu
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,290 | $69,750 |
$18,290
281,400
kWh
|
- | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $42,330 | $164,300 |
$39,000
600,000
kWh
|
$3,330
-
kW-mo/yr
|
- | |
05 | 2.4226: Use / purchase optimum sized compressor | $8,400 | $46,500 |
$6,050
93,060
kWh
|
$2,350
-
kW-mo/yr
|
- | |
06 | 2.2628: Utilize a less expensive cooling method | $13,980 | $92,000 |
$13,980
215,150
kWh
|
- | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $57,540 | $1,325,000 |
$57,540
885,200
kWh
|
- | - | |
TOTAL RECOMMENDED | $198,990 | $1,816,900 |
$121,530
1,869,660
kWh
|
$4,110
-
kW-mo/yr
|
$73,350
-
MMBtu
|
||
TOTAL IMPLEMENTED | $118,160 | $1,559,050 |
$114,830
1,766,600
kWh
|
$3,330
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs