ITAC Assessment: DL0143
ITAC logo
ITAC Assessment: DL0143
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Cellulosic Sugar
NAICS 325110: Petrochemical Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 45
Plant Area 40,000
ft2
Annual Production 100,000
ton
Production Hrs. Annual 3,640
hrs
Location (State) Pennsylvania

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $78,421 930,048
kWh
Electricity Demand $21,745 3,029
kW-mo/yr
Electricity Fees $2,070 -
Natural Gas $39,455 4,427
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,821 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,335

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7314: Reduce ventilation air $12,970 - $7,980
95,000
kWh
$4,990
-
MMBtu
02 2.7111: Reduce illumination to minimum necessary levels $1,928 - $1,928
22,950
kWh
-
03 2.6212: Turn off equipment during breaks, reduce operating time $1,030 $1,000 $1,030
12,280
kWh
-
04 2.7311: Ventilation system to shut off when room is not in use $1,988 - $428
5,090
kWh
$1,560
-
MMBtu
05 2.7311: Ventilation system to shut off when room is not in use $2,468 $200 $482
5,730
kWh
$1,986
-
MMBtu
06 2.7261: Install timers and/or thermostats $1,582 $3,000 - $1,582
-
MMBtu
07 2.7261: Install timers and/or thermostats $855 - - $855
-
MMBtu
TOTAL RECOMMENDED $22,821 $4,200 $11,848
141,050
kWh
$10,973
-
MMBtu
TOTAL IMPLEMENTED $17,335 $3,000 $9,908
117,950
kWh
$7,427
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs