Assessment Year | 2013 |
---|---|
Principal Product | Fresh and frozen seafood |
NAICS | 311422: Specialty Canning |
SIC | 2032: Canned Specialties |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
200,000
ft2
|
Annual Production | 9,999,999
units
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $826,412 | 8,563,200 |
kWh
|
$0.097 |
Natural Gas | $602,202 | 103,087 |
MMBtu
|
$5.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $89,384 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,714 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|
01 | 3.4115: Recover and reuse cooling water | $33,000 | $135,000 | - | - |
$33,000
-
Tgal
|
|
02 | 2.2136: Install / repair insulation on steam lines | $3,884 | $2,770 | - |
$3,884
-
MMBtu
|
- | |
03 | 2.2136: Install / repair insulation on steam lines | $7,300 | $4,043 | - |
$7,300
-
MMBtu
|
- | |
04 | 2.2136: Install / repair insulation on steam lines | $2,800 | $7,588 | - |
$2,800
-
MMBtu
|
- | |
05 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $25,100 | $9,800 | - |
$25,100
-
MMBtu
|
- | |
06 | 2.4224: Upgrade controls on compressors | $8,270 | $7,000 |
$8,270
85,500
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,030 | $18,354 |
$9,030
93,076
kWh
|
- | - | |
TOTAL RECOMMENDED | $89,384 | $184,555 |
$17,300
178,576
kWh
|
$39,084
-
MMBtu
|
$33,000
-
Tgal
|
||
TOTAL IMPLEMENTED | $15,714 | $28,712 |
$9,030
93,076
kWh
|
$6,684
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs