| Assessment Year | 2013 |
|---|---|
| Principal Product | Zirconium-based chemicals |
| NAICS | 339999: All Other Miscellaneous Manufacturing |
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 55 |
| Plant Area |
2,637,000
ft2
|
| Annual Production | 9,000,000
lb
|
| Production Hrs. Annual | 5,760
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $442,900 | 3,750,000 |
kWh
|
$0.12 |
| Natural Gas | $289,900 | 32,130 |
MMBtu
|
$9.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $137,864 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $29,934 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $48,700 | $2,341 | - |
$48,700
-
MMBtu
|
|
| 02 | 2.1394: Replace steam jets on vacuum system with electric motor driven vacuum pumps | $8,930 | $2,820 |
$8,930
75,700
kWh
|
- | |
| 03 | 2.4322: Use or replace with energy efficient substitutes | $8,900 | $40,000 |
$8,900
75,200
kWh
|
- | |
| 04 | 2.4226: Use / purchase optimum sized compressor | $4,800 | $5,850 |
$4,800
41,100
kWh
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $21,034 | $13,739 |
$21,034
178,259
kWh
|
- | |
| 06 | 2.4224: Upgrade controls on compressors | $32,800 | $16,000 |
$32,800
278,000
kWh
|
- | |
| 07 | 2.2414: Use waste heat from hot flue gases to preheat | $12,700 | $33,000 | - |
$12,700
-
MMBtu
|
|
| TOTAL RECOMMENDED | $137,864 | $113,750 |
$76,464
648,259
kWh
|
$61,400
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $29,934 | $53,739 |
$29,934
253,459
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs