| Assessment Year | 2013 |
|---|---|
| Principal Product | Custom Pharmaceutical |
| NAICS | 325412: Pharmaceutical Preparation Manufacturing |
| SIC | 2834: Pharmaceutical Preparations |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
74,000
ft2
|
| Annual Production | 100
pieces
|
| Production Hrs. Annual | 3,120
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $597,520 | 4,350,320 |
kWh
|
$0.14 |
| Natural Gas | $137,749 | 13,764 |
MMBtu
|
$10.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $71,140 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $57,280 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7314: Reduce ventilation air | $31,820 | $3,200 |
$27,420
200,240
kWh
|
$4,400
-
MMBtu
|
|
| 02 | 2.7263: Lower compressor pressure through a/c system modification | $25,460 | $100 |
$25,460
185,830
kWh
|
- | |
| 03 | 2.7316: Centralize control of exhaust fans to ensure their shutdown, or establish program to ensure manual shutdown | $4,740 | $100 |
$4,740
34,600
kWh
|
- | |
| 04 | 2.6231: Utilize controls to operate equipment only when needed | $4,500 | $510 |
$4,500
32,700
kWh
|
- | |
| 05 | 2.7233: Use properly designed and sized hvac equipment | $4,300 | $37,600 |
$4,300
31,400
kWh
|
- | |
| 06 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $320 | $185 |
$320
2,340
kWh
|
- | |
| TOTAL RECOMMENDED | $71,140 | $41,695 |
$66,740
487,110
kWh
|
$4,400
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $57,280 | $3,300 |
$52,880
386,070
kWh
|
$4,400
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs