| Assessment Year | 2012 |
|---|---|
| Principal Product | Corrugated paper sheets |
| NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
| SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 60 |
| Plant Area |
120,000
ft2
|
| Annual Production | 1,200,000
thousand feet
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | New Jersey |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $208,287 | 1,810,200 |
kWh
|
$0.12 |
| Electricity Demand | $44,973 | 7,278 |
kW-mo/yr
|
$6.18 |
| Electricity Fees | $4,800 | - |
|
- |
| Natural Gas | $349,851 | 42,151 |
MMBtu
|
$8.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $63,570 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,350 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,450 | $39,400 |
$14,450
125,700
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,180 | $1,500 |
$1,180
10,270
kWh
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,580 | $2,500 |
$14,580
126,800
kWh
|
- | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,770 | $300 |
$1,770
15,400
kWh
|
- | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $10,500 | $16,000 | - |
$10,500
-
MMBtu
|
|
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,830 | $5,500 |
$8,830
76,750
kWh
|
- | |
| 07 | 2.6218: Turn off equipment when not in use | $7,530 | $100 |
$7,530
65,500
kWh
|
- | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $890 | $800 |
$890
7,750
kWh
|
- | |
| 09 | 2.2437: Recover waste heat from equipment | $2,030 | $300 | - |
$2,030
-
MMBtu
|
|
| 10 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $1,810 | $325 | - |
$1,810
-
MMBtu
|
|
| TOTAL RECOMMENDED | $63,570 | $66,725 |
$49,230
428,170
kWh
|
$14,340
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $16,350 | $2,800 |
$16,350
142,200
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs