ITAC Assessment: DL0089
ITAC logo
ITAC Assessment: DL0089
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Aerospace Sealants
NAICS 325520: Adhesive Manufacturing
SIC 2891: Adhesives and Sealants
Sales Range $1
M
to 5
M
# of Employees 60
Plant Area 60,000
ft2
Annual Production 850,000
pieces
Production Hrs. Annual 3,390
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,479 645,240
kWh
Natural Gas $21,387 2,073
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,250 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $28,225

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7447: Install vinyl strip / high speed / air curtain doors $14,050 $6,800 $1,370
10,000
kWh
$12,680
-
MMBtu
02 2.7233: Use properly designed and sized hvac equipment $7,675 $27,000 $7,675
50,100
kWh
-
03 2.7221: Lower temperature during the winter season and vice-versa $5,880 - - $5,880
-
MMBtu
04 2.7314: Reduce ventilation air $620 $81 $120
880
kWh
$500
-
MMBtu
05 2.2515: Use optimum thickness insulation $1,025 $2,275 $1,025
7,500
kWh
-
TOTAL RECOMMENDED $29,250 $36,156 $10,190
68,480
kWh
$19,060
-
MMBtu
TOTAL IMPLEMENTED $28,225 $33,881 $9,165
60,980
kWh
$19,060
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs