| Assessment Year | 2010 |
|---|---|
| Principal Product | Sheet metal manufacturing |
| NAICS | 332322: Sheet Metal Work Manufacturing |
| SIC | 3444: Sheet Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 115 |
| Plant Area |
73,851
ft2
|
| Annual Production | 415,000
lb
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Maryland |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $67,249 | 703,120 |
kWh
|
$0.096 |
| Natural Gas | $5,234 | 439 |
MMBtu
|
$11.92 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,042 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,920 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,623 | $100 |
$1,623
16,069
kWh
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,070 | $300 |
$3,070
30,401
kWh
|
- | |
| 03 | 2.6232: Install set-back timers | $1,236 | $300 |
$711
7,031
kWh
|
$525
-
MMBtu
|
|
| 04 | 2.2514: Cover open tanks | $263 | $275 |
$263
2,600
kWh
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,850 | $34,600 |
$9,850
98,000
kWh
|
- | |
| TOTAL RECOMMENDED | $16,042 | $35,575 |
$15,517
154,101
kWh
|
$525
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $12,920 | $34,900 |
$12,920
128,401
kWh
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs