| Assessment Year | 1985 |
|---|---|
| Principal Product | PROCESSED MOLYBDENUM ORE |
| NAICS |
n/a
|
| SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
n/a
|
| Annual Production | 7,986,000
ton
|
| Production Hrs. Annual | 6,048
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $5,962,975 | 134,199,885 |
kWh
|
$0.044 |
| Coal | $270,025 | 339,104 |
MMBtu
|
$0.80 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $93,165 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $85,281 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Coal Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $6,865 | $7,500 |
$6,865
167,644
kWh
|
- | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $76,640 | $40,000 | - |
$76,640
-
MMBtu
|
|
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $7,884 | $76,000 | - |
$7,884
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,236 | - |
$1,236
30,188
kWh
|
- | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $540 | - |
$540
13,189
kWh
|
- | |
| TOTAL RECOMMENDED | $93,165 | $123,500 |
$8,641
211,021
kWh
|
$84,524
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $85,281 | $47,500 |
$8,641
211,021
kWh
|
$76,640
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs