ITAC Assessment: DL0022
ITAC logo
ITAC Assessment: DL0022
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Laundry Services
NAICS 812320: Drycleaning and Laundry Services (except Coin-Operated)
SIC 7211: Power Laundries, Family and Commercial
Sales Range $10
M
to 50
M
# of Employees 164
Plant Area 44,000
ft2
Annual Production 11,000,000
pieces
Production Hrs. Annual 5,200
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $177,600 1,348,425
kWh
Electricity Demand $7,664 3,121
kW-mo/yr
Natural Gas $300,181 22,691
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $85,427 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,928

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Water Consumption Savings
01 2.1212: Operate boilers on high fire setting $10,038 - - $10,038
-
MMBtu
- -
02 3.4151: Minimize water usage $18,580 $10,000 - - $8,066
-
Tgal
$10,514
-
Tgal
03 2.7142: Utilize higher efficiency lamps and/or ballasts $12,452 $38,199 $12,452
99,091
kWh
- - -
04 2.1224: Replace boiler $39,920 $112,000 - $39,920
-
MMBtu
- -
05 2.4221: Install compressor air intakes in coolest locations $2,579 - $2,579
20,635
kWh
- - -
06 2.2136: Install / repair insulation on steam lines $1,858 $1,000 - $1,858
-
MMBtu
- -
TOTAL RECOMMENDED $85,427 $161,199 $15,031
119,726
kWh
$51,816
-
MMBtu
$8,066
-
Tgal
$10,514
-
Tgal
TOTAL IMPLEMENTED $42,928 $49,199 $12,452
99,091
kWh
$11,896
-
MMBtu
$8,066
-
Tgal
$10,514
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Disposal Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs