| Assessment Year | 2008 |
|---|---|
| Principal Product | Beer |
| NAICS | 312120: Breweries |
| SIC | 2082: Malt Beverages |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
50,000
ft2
|
| Annual Production | 180,000
pieces
|
| Production Hrs. Annual | 8,766
hrs
|
| Location (State) | Delaware |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $14,029 | 180,008 |
kWh
|
$0.078 |
| Electricity Demand | $2,800 | 383 |
kW-mo/yr
|
$7.31 |
| Other Energy | $313,000 | 16,200 |
MMBtu
|
$19.32 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $96,800 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $31,430 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $20,000 | $400 | - | - |
$20,000
-
MMBtu
|
|
| 02 | 2.4221: Install compressor air intakes in coolest locations | $2,400 | $3,500 | - |
$2,400
-
kW-mo/yr
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,500 | $20,000 |
$19,500
210,000
kWh
|
- | - | |
| 04 | 2.7131: Add area lighting switches | $370 | $1,500 |
$370
4,000
kWh
|
- | - | |
| 05 | 2.2136: Install / repair insulation on steam lines | $5,911 | $2,500 | - | - |
$5,911
-
MMBtu
|
|
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $14,000 | $16,000 | - | - |
$14,000
-
MMBtu
|
|
| 07 | 2.1224: Replace boiler | $13,000 | $20,000 | - | - |
$13,000
-
MMBtu
|
|
| 08 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $15,400 | $27,000 | - | - |
$15,400
-
MMBtu
|
|
| 09 | 2.2425: Use flue gases to heat process or service water | $2,970 | $10,000 | - | - |
$2,970
-
MMBtu
|
|
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,249 | $18,000 |
$3,249
34,938
kWh
|
- | - | |
| TOTAL RECOMMENDED | $96,800 | $118,900 |
$23,119
248,938
kWh
|
$2,400
-
kW-mo/yr
|
$71,281
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $31,430 | $45,500 |
$23,119
248,938
kWh
|
$2,400
-
kW-mo/yr
|
$5,911
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Energy Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs