| Assessment Year | 2008 |
|---|---|
| Principal Product | Monomers, Polyester Acrylates,Sarbox |
| NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $100 M to 500M |
| # of Employees | 95 |
| Plant Area |
25,000
ft2
|
| Annual Production | 1,000
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $502,960 | 9,370,590 |
kWh
|
$0.054 |
| Electricity Demand | $214,977 | 1,286 |
kW-mo/yr
|
$167.17 |
| Natural Gas | $1,241,710 | 127,804 |
MMBtu
|
$9.72 |
| Fuel Oil #2 | $578,359 | 38,502 |
MMBtu
|
$15.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $158,914 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $158,914 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $18,300 | - |
$3,000
37,500
kWh
|
$15,300
-
MMBtu
|
|
| 02 | 2.7135: Install occupancy sensors | $2,396 | $285 |
$2,396
29,952
kWh
|
- | |
| 03 | 2.2511: Insulate bare equipment | $108,300 | $104,800 | - |
$108,300
-
MMBtu
|
|
| 04 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $24,218 | $25,000 | - |
$24,218
-
MMBtu
|
|
| 05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $5,700 | $10,000 |
$5,700
43,575
kWh
|
- | |
| TOTAL RECOMMENDED | $158,914 | $140,085 |
$11,096
111,027
kWh
|
$147,818
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $158,914 | $140,085 |
$11,096
111,027
kWh
|
$147,818
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs