ITAC Assessment: CO0345
ITAC logo
ITAC Assessment: CO0345
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Printed circuit boards
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $10
M
to 50
M
# of Employees 290
Plant Area 66,000
ft2
Annual Production 380,000
pieces
Production Hrs. Annual 6,864
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $290,677 6,451,348
kWh
Natural Gas $21,920 5,746
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $170,800 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,840

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
01 3.5242: Recover metals from spent solutions and recycle $153,900 $340,000 - - $3,080
-
Tgal
$150,820
02 2.7142: Utilize higher efficiency lamps and/or ballasts $13,920 $44,400 $13,920
323,271
kWh
- - -
03 2.4133: Use most efficient type of electric motors $1,520 $2,490 $1,520
37,222
kWh
- - -
04 2.4221: Install compressor air intakes in coolest locations $1,320 $490 $1,320
33,118
kWh
- - -
05 2.2437: Recover waste heat from equipment $140 $280 - $140
-
MMBtu
- -
TOTAL RECOMMENDED $170,800 $387,660 $16,760
393,611
kWh
$140
-
MMBtu
$3,080
-
Tgal
$150,820
TOTAL IMPLEMENTED $2,840 $2,980 $2,840
70,340
kWh
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs