| Assessment Year | 1995 |
|---|---|
| Principal Product | Printed circuit boards |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 290 |
| Plant Area |
66,000
ft2
|
| Annual Production | 380,000
pieces
|
| Production Hrs. Annual | 6,864
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $290,677 | 6,451,348 |
kWh
|
$0.045 |
| Natural Gas | $21,920 | 5,746 |
MMBtu
|
$3.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $170,800 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,840 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.5242: Recover metals from spent solutions and recycle | $153,900 | $340,000 | - | - |
$3,080
-
Tgal
|
$150,820 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,920 | $44,400 |
$13,920
323,271
kWh
|
- | - | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $1,520 | $2,490 |
$1,520
37,222
kWh
|
- | - | - | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,320 | $490 |
$1,320
33,118
kWh
|
- | - | - | |
| 05 | 2.2437: Recover waste heat from equipment | $140 | $280 | - |
$140
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $170,800 | $387,660 |
$16,760
393,611
kWh
|
$140
-
MMBtu
|
$3,080
-
Tgal
|
$150,820 | ||
| TOTAL IMPLEMENTED | $2,840 | $2,980 |
$2,840
70,340
kWh
|
- | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs