ITAC Assessment: CW0122
ITAC logo
ITAC Assessment: CW0122
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Excavators and Vacuum Trucks
NAICS 333120: Construction Machinery Manufacturing
SIC 3531: Construction Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 422,753
ft2
Annual Production 6,507
ton
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $335,641 4,389,000
kWh
Natural Gas $272,862 123,540
MMBtu
Waste Disposal Costs
Water Usage $9,317 686
Tgal
Water Disposal $9,689 686
Tgal
TOTAL YEARLY COSTS $627,509
RECOMMENDED SAVINGS* $199,286 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Usage Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings
01 3.4113: Treat and reuse rinse waters $11,974 $2,500 - - $5,868
-
Tgal
$6,106
-
Tgal
-
02 2.2437: Recover waste heat from equipment $3,767 $400 $299
3,929
kWh
$3,469
-
MMBtu
- - -
03 3.2173: Convert to robotic painting $102,960 $48,500 - - - - $102,960
04 4.652: Replace existing equipment with more suitable substitutes $25,171 $73,990 $25,171
331,200
kWh
- - - -
05 2.4224: Upgrade controls on compressors $13,037 $60,000 $13,037
171,543
kWh
- - - -
06 2.7492: Use proper thickness of insulation on building envelope $42,376 $188,648 - $42,376
-
MMBtu
- - -
TOTAL RECOMMENDED $199,286 $374,038 $38,507
506,672
kWh
$45,845
-
MMBtu
$5,868
-
Tgal
$6,106
-
Tgal
$102,960
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Usage Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs