Assessment Year | 2022 |
---|---|
Principal Product | Stump grinders, Forestry mulchers |
NAICS | 333120: Construction Machinery Manufacturing |
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
400,000
ft2
|
Annual Production | 5,226,553
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,285 | 2,206,532 |
kWh
|
$0.044 |
Electricity Demand | $37,840 | 5,398 |
kW-mo/yr
|
$7.01 |
Electricity Fees | $232,075 | - |
|
- |
Natural Gas | $95,141 | 17,546 |
MMBtu
|
$5.42 |
TOTAL YEARLY COSTS | $462,341 | |||
RECOMMENDED SAVINGS* | $204,811 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $109,741 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $3,129 | $400 |
$1,332
30,201
kWh
|
$784
-
kW-mo/yr
|
$1,013
-
MMBtu
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,231 | $26,058 |
$14,231
332,693
kWh
|
- | - | - | - | |
03 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $3,746 | $265 | - | - |
$3,746
-
MMBtu
|
- | - | |
04 | 3.2173: Convert to robotic painting | $93,600 | $33,000 | - | - | - | $93,600 | - | |
05 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $31,088 | $86,330 | - | - |
$31,088
-
MMBtu
|
- | - | |
06 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $461 | $517 | - | - |
$461
-
MMBtu
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,581 | - |
$1,581
35,852
kWh
|
- | - | - | - | |
08 | 2.4221: Install compressor air intakes in coolest locations | $925 | $810 |
$925
20,977
kWh
|
- | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $608 | $165 |
$608
13,785
kWh
|
- | - | - | - | |
10 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $6,639 | $5,500 | - | - | - | - | $6,639 | |
11 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $545 | $90 | - | - | - | - | $545 | |
12 | 3.5316: Contract a wood pallet recycling company | $48,258 | $14,344 | - | - | - | - | $48,258 | |
TOTAL RECOMMENDED | $204,811 | $167,479 |
$18,677
433,507
kWh
|
$784
-
kW-mo/yr
|
$36,308
-
MMBtu
|
$93,600 | $55,442 | ||
TOTAL IMPLEMENTED | $109,741 | $133,579 |
$17,752
412,530
kWh
|
$784
-
kW-mo/yr
|
$36,308
-
MMBtu
|
- | $54,897 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs