| Assessment Year | 2022 |
|---|---|
| Principal Product | Specialty turbomachinery |
| NAICS | 333996: Fluid Power Pump and Motor Manufacturing |
| SIC | 3594: Fluid Power Pumps and Motors |
| Sales Range | $50 M to 100M |
| # of Employees | 160 |
| Plant Area |
90,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 5,500
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $94,764 | 1,764,194 |
kWh
|
$0.054 |
| Electricity Demand | $91,554 | 5,846 |
kW-mo/yr
|
$15.66 |
| Electricity Fees | $16,440 | - |
|
- |
| Natural Gas | $19,561 | 2,584 |
MMBtu
|
$7.57 |
| TOTAL YEARLY COSTS | $222,319 | |||
| RECOMMENDED SAVINGS* | $94,112 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,629 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $83,984 | $462,079 |
$43,845
816,253
kWh
|
$9,530
-
kW-mo/yr
|
$30,609 | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,833 | $2,733 |
$2,343
43,626
kWh
|
$1,490
-
kW-mo/yr
|
- | |
| 03 | 2.7135: Install occupancy sensors | $1,478 | $359 |
$1,478
27,515
kWh
|
- | - | |
| 04 | 2.4226: Use / purchase optimum sized compressor | $3,318 | $16,143 |
$1,709
31,830
kWh
|
$1,609
-
kW-mo/yr
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,499 | $200 |
$374
6,961
kWh
|
$1,125
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $94,112 | $481,514 |
$49,749
926,185
kWh
|
$13,754
-
kW-mo/yr
|
$30,609 | ||
| TOTAL IMPLEMENTED | $8,629 | $19,235 |
$5,530
102,971
kWh
|
$3,099
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs