ITAC Assessment: CO0735
ITAC logo
ITAC Assessment: CO0735
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Family Entertainment Center
NAICS 713950: Bowling Centers
SIC 7933: Bowling Centers
Sales Range $1
M
to 5
M
# of Employees 100
Plant Area 52,300
ft2
Annual Production 1,000
units
Production Hrs. Annual 5,320
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,203 1,003,200
kWh
Electricity Demand $53,322 2,533
kW-mo/yr
Electricity Fees $876 -
Natural Gas $22,060 4,042
MMBtu
TOTAL YEARLY COSTS $143,461
RECOMMENDED SAVINGS* $13,250 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system $4,910 $31,560 $1,290
19,200
kWh
$3,620
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,020 $13,690 $1,750
26,200
kWh
$1,340
-
kW-mo/yr
$480 $450
03 2.9114: Use solar heat to make electricty $2,820 $14,180 $2,530
37,700
kWh
$290
-
kW-mo/yr
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,500 $1,860 $1,050
15,600
kWh
$450
-
kW-mo/yr
- -
TOTAL RECOMMENDED $13,250 $61,290 $6,620
98,700
kWh
$5,700
-
kW-mo/yr
$480 $450
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs