ITAC Assessment: CO0726
ITAC logo
ITAC Assessment: CO0726
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Aftermarket Mining Equipment Components
NAICS 333131: Mining Machinery and Equipment Manufacturing
SIC 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 88
Plant Area 83,400
ft2
Annual Production 10,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Montana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,276 1,051,576
kWh
Electricity Demand $61,250 5,449
kW-mo/yr
Electricity Fees $1,624 -
Natural Gas $17,388 2,975
MMBtu
Waste Disposal Costs
Other Liquid (non-haz) $3,300 3,250
gal
TOTAL YEARLY COSTS $158,838
RECOMMENDED SAVINGS* $16,910 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $680 $1,630 $490
7,400
kWh
$190
-
kW-mo/yr
- - - -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $380 $660 $240
3,600
kWh
$140
-
kW-mo/yr
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $10,470 $36,440 $7,310
109,800
kWh
$3,660
-
kW-mo/yr
- - $270 $(-770.0)
04 3.6124: Burn waste oil for heat $5,380 $5,270 - - $2,080
-
MMBtu
$3,300
-
gal
- -
TOTAL RECOMMENDED $16,910 $44,000 $8,040
120,800
kWh
$3,990
-
kW-mo/yr
$2,080
-
MMBtu
$3,300
-
gal
$270 $(-770.0)
TOTAL IMPLEMENTED - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs