| Assessment Year | 2016 |
|---|---|
| Principal Product | Aftermarket Mining Equipment Components |
| NAICS | 333131: Mining Machinery and Equipment Manufacturing |
| SIC | 3532: Mining Machinery and Equipment, Except Oil and Gas Field Machinery and Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 88 |
| Plant Area |
83,400
ft2
|
| Annual Production | 10,000
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | Montana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $75,276 | 1,051,576 |
kWh
|
$0.072 | |
| Electricity Demand | $61,250 | 5,449 |
kW-mo/yr
|
$11.24 | |
| Electricity Fees | $1,624 | - |
|
- | |
| Natural Gas | $17,388 | 2,975 |
MMBtu
|
$5.84 | |
| Waste Disposal Costs | |||||
| Other Liquid (non-haz) | $3,300 | 3,250 |
gal
|
$1.02 | |
| TOTAL YEARLY COSTS | $158,838 | ||||
| RECOMMENDED SAVINGS* | $16,910 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $680 | $1,630 |
$490
7,400
kWh
|
$190
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $380 | $660 |
$240
3,600
kWh
|
$140
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,470 | $36,440 |
$7,310
109,800
kWh
|
$3,660
-
kW-mo/yr
|
- | - | $270 | $(-770.0) | |
| 04 | 3.6124: Burn waste oil for heat | $5,380 | $5,270 | - | - |
$2,080
-
MMBtu
|
$3,300
-
gal
|
- | - | |
| TOTAL RECOMMENDED | $16,910 | $44,000 |
$8,040
120,800
kWh
|
$3,990
-
kW-mo/yr
|
$2,080
-
MMBtu
|
$3,300
-
gal
|
$270 | $(-770.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs